Introduction
The URS and the FAT answer different questions.The URS defines what the line must do and under what conditions;The FAT demonstrates, before shipping, that the line meets those requirements with the actual product and packaging.Mixing both things produces documents that are neither useful for purchasing nor verification.
This article separates the requirements that belong to the URS from the evidence that must be reviewed in the FAT, with a list applicable to intramammary filling lines.It is aimed at buyers and validation teams who need a verifiable document and proof to confirm it.

*URS with verifiable requirements and acceptance criteria.*
What goes in the URS
The URSIt contains functional, process, packaging, cleaning, documentation and service requirements.Each requirement must be verifiable: if it cannot be verified, it is not a requirement, it is a wish.
The URS does not include technical solutions.It doesn't say "piston pump" or "servo";It says what dose, what tolerance and what conditions the system must meet.
The URS is written before quoting.If it is written later, it adapts to what the supplier offered and stops protecting the buyer.
What goes in the FAT
The FAT contains tests, criteria and records.Each test must correspond to a URS requirement and produce evidence.
The FAT does not repeat the URS: it verifies it.If a requirement has no proof, the FAT is incomplete;if a test has no requirement, the FAT is inflated.
The FAT is run with the actual product and packaging, or with an agreed upon and declared substitute.
Applicator Functional Requirements
Applicator requirements include geometry, material, tolerances, and behavior.The URS must declare which applicators will be produced and with what variability.
It must also declare the filling orientation, the type of plunger and the type of cap, because each one conditions the tooling and the stations.
The FAT must demonstrate that the applicator is fed, filled, closed and discharged withoutdamage.

*Matrix linking each requirement to its evidence in FAT.*
Process requirements
Process requirements include dose, tolerance, rate, viscosity range and temperature.They must be expressed with units and conditions.
The URS must declare the entire range, not just the nominal point.The FAT must test at least the extremes of the range.
Shutdown behavior must also be declared: what is discarded and what is checked on restart.
Cleaning and changeover requirements
The URS must declare the products to be manufactured, the changeover frequency and the cleaning methodexpected.
The FAT must demonstrate that disassembly is possible in the planned time and that critical areas are accessible.
A cleaning requirement without verification criteria is not verifiable.
Documentation and service requirements
The URS must list the deliverable documentation:plans, manuals, spare parts list, protocols and records.
You must also declare the services available in the plant and the environmental conditions, because they condition the installation.
The FAT must review that the documentation exists and corresponds to the tested machine.
Table of requirements and evidence
| Requirement | Category | Verifiable criterion | Evidence in FAT | Responsible |
|---|---|---|---|---|
| Dose in range | Process | Value and tolerance per product | Weighed per batch | Quality |
| Closing | Process | Retention according to test | Trial record | Quality |
| Damage-free applicator | Container | Mark-free inspection | Samples and photos | Production |
| Format change | Operation | Time and first piece | Timed record | Engineering |
| Cleaning | Quality | Access and time | Checklist | Quality |
| Alarms | Security | Correct answer | Interlock test | Engineering |
| Documentation | Documentary | Complete delivery | List of documents | Project |
How to write a verifiable requirement
A verifiable requirement has a subject, condition, criterion and method.“The line must fill applicators” is not verifiable;"the line must fill 5 mL applicators with a dose of X ± Y, measured by weighing, at a speed of Z" is.
The condition includes the product, packaging and environment.Without condition, the criterion cannot be reproduced.
The method defines the instrument and the procedure.Without method, the result is debatable.
Acceptance criteria by type of requirement
An acceptance criterion is not written the same for a process requirement as for a documentary one.The criterion must correspond to the nature of what is being verified, and this correspondence conditions the proof, the registration and the signature.Applying the same formula to all requirements produces ambiguous criteria in some cases and disproportionate in others.
In process requirements, such as dose or closure, the criterion is a magnitude with unit, tolerance and measurement conditions.You must indicate the instrument, the number of samples and the treatment of the values that are left out.Without that precision, the result is discussed after the test rather than resolved beforehand.
In packaging and operational requirements, such as applicator integrity or format change, the criterion is usually an inspection with a closed list of defects and a reference time.That list must enumerate what is considered a defect and what is considered acceptable, because visual inspection without prior definition depends on who is looking.
In documentary and service requirements, the criterion is the existence, correspondence and integrity of the deliverable.It is accepted when the document exists, corresponds to the machine tested and is in the agreed language and format.King Pack can review with the client what type of criteria corresponds to each requirement and document it in writing before testing.
How to handle a deviation in FAT
A deviation is a result that does not meet the agreed criteria or a test that cannot be executed under the expected conditions.It is not an opinion or a nuisance: it is a recorded fact that requires a decision before closing the acceptance.The FAT does not end when the deviation appears, but when the deviation is resolved and documented.
The record must identify the affected requirement, the test, the execution condition, the result obtained and the available evidence.It is worth adding who detected it, when and what was done with the material produced during the test.A record without this data requires repeating the test to reconstruct what happened.
The action depends on the cause.If the failure is a method failure, the procedure is corrected and the test is repeated.If it is an adjustment, the parameter is modified and it is measured again with the same criteria.If it is design, the decision corresponds to the client and the supplier, and usually implies a change in scope with an impact on the deadline.
Every accepted deviation requires a written concession: what is accepted, with what limit and under what monitoring condition.King Pack can document the deviation, propose the action and confirm closure in writing, but final acceptance is up to the customer.
What requirements are verified during commissioning
Not all requirements can be tested in the factory.The commissioning verifies those that depend on the installation, the plant services or the real production environment, and confirms that what has been tested in FAT is maintained in its final location.
Among them are the connection to the available services, the integration with the client's systems, the response of the interlocks in their final location and the behavior of the line with the product and the packaging in plant conditions.The training of personnel and the delivery of final documentation are also verified.
The start-up does not repeat the FAT.If a requirement was tested and accepted in the factory, the plant checks that the acceptance condition is preserved;If it is not preserved, a deviation is opened with the same treatment.Repeating already closed tests without reason adds time and does not provide new evidence.
The start-up protocol must declare what is verified, with what criteria, who executes and who signs.King Pack can propose this protocol and document the results, and confirm in writing which requirements are covered at each stage.
Traceability between requirement and evidence
Traceability is the ability to respond, for any requirement, with what test it was verified, what result was obtained and who signed it.Without that string, the FAT is a collection of records and the URS a list of intents.
The practical tool is an array with an identifier per requirement and a reference to the test and the corresponding record.The identifier must remain stable between versions, because it is what allows the revised URS to be compared with the executed FAT without rebuilding the history.
The array is built at the same time as the protocol, not at the end.If it is assembled later, requirements without proof and tests without requirement appear, and the correction arrives when there is no longer room to repeat the test.
Each evidence must indicate the version of the document and the machine, the date, the executor and the person responsible for the review.When a requirement changes, the matrix should show the old and new version, so you know which evidence supports which text and since when.King Pack can document this matrix and confirm the correspondence in writing, although approval of the criteria remains with the client.
Role of the client during the FAT
The client does not attend the FAT as a spectator.Their role is to approve the protocol before the test, provide the product and packaging, designate the person with authority to accept or reject, and sign the result.Without that presence, acceptance remains in the hands of whoever executes.
Before testing, the client checks that each criterion is as agreed upon and that the method is reproducible.During execution, observe the conditions and record what you consider relevant, without introducing new criteria as you go.Changing a criterion mid-test invalidates the comparison with the requirements.
At closing, the client signs the minutes with the deviations and concessions.If you cannot sign, there must be a record of who signs on your behalf and to what extent.A signature without a defined scope does not protect either party.
King Pack can review the protocol with the client before testing and document observations in writing, so that the signature is based on a text known to both parties.Without this prior preparation, the FAT becomes a demonstration and not a verification.
What to do if the product is not available
It is common that the actual product is not available on the date of the FAT.The solution is not to try anything or postpone without judgment: it is to agree on a substitute, declare it, and limit the scope of what the test demonstrates.
The substitute must be characterized before testing: what it shares with the real product and how it differs.This comparison defines which tests remain valid and which must be repeated.If the difference affects the viscosity, density or behavior of the container, the dose test loses some of its value.
Product-dependent tests are moved to start-up or a complementary FAT.Those that depend on the machine and the packaging can be executed with the substitute and registered as such, without presenting them as equivalent.
The agreement must be in writing, with the list of affected tests and the person responsible for repeating them.It is also advisable to set the deadline for repeating them, because a pending test without a deadline becomes a tacit acceptance.King Pack can document that agreement and confirm in writing what is outstanding, but the decision on accepted risk is up to the customer.
How to review the URS with the supplier
Reviewing the URS with the supplier does not involve the supplier rewriting it.It consists of a joint reading, requirement by requirement, to detect ambiguities, non-verifiable requirements and technical solutions disguised as a need.
The review is done in a session with the versioned URS on the table and a person responsible for each part.Each requirement is read aloud and three questions are answered: what it means, how it is verified, and who accepts it.If any response is not immediate, the requirement is marked for correction before continuing.The objective is not to reduce the number of requirements, but to leave each one in a position to be tested and signed.
The result is recorded in a record with the agreed changes, the postponed requirements and the open questions with a deadline.The revised URS becomes the reference version for the offer and for the FAT protocol, and any subsequent changes follow the same circuit.
King Pack can review the URS with the client, propose comments and document the review record.The requirements, their priority and their acceptance remain the responsibility of the client.
Frequent errors
- Write the URS after the offer. It adapts to what is offered.
- Include technical solutions in the URS. The function is lost.
- Requirementswithout criteria. Cannot be verified.
- FAT without real product. Does not demonstrate behavior.
- Do not link FAT and URS. Requirements remain without evidence.
- Accept incomplete documentation. Go-live is delayed.
How King Pack supports
King Pack can review the URS with the customer and propose the corresponding FAT protocol, with criteria and records.The scope includes machine documentation, personnel training and start-up support.Capacities and limits are confirmed in writing for each project.
Frequently Asked Questions
Who writes the URS? The customer, with technical support.It is your requirements document.
Can the FAT replace the URS? No. The FAT verifies requirements;it does not define them.
Can the URS be changed after the FAT? You can, but it involves reviewing the scope and evidence.
What happens if a requirement cannot be tested in FAT? Is it moved to go-live or documented as a limitation.
Does the URS include price?No. It includes technical and service requirements.
How many requirements should a URS have? Those necessary to describe the process.A long document is not better.
Does the FAT have to be repeated if the product changes? Critical tests do, because behavior can change.
Who signs the FAT minutes? The client and the supplier, each with their declared scope.The signature that accepts is that of the client.
Is an observation the same as a deviation? No. The observation is recorded without blocking the acceptance;deviation requires a decision and documented closure.
Related technical resources
For further specification, review intramammary syringe filling line and specification of a syringe linepreloaded.These resources help finalize samples, scope, and acceptance criteria before requesting a proposal.

*Running a dose test during factory acceptance.*
Conclusion
TheURS defines and FAT demonstrates.Separating the two avoids documents that are useless and tests that do not verify.A list of verifiable requirements and a linked FAT turn the purchase into a controlled project.