Introduction
The auxiliary services are the part of the project that no one reviews until the machine arrives at the plant.Electricity, compressed air, vacuum, water, drainage and environmental conditions determine whether the line starts in days or weeks.A correctly installed machine with insufficient services produces the same defects as a poorly adjusted machine.
This article lists the services that must be provided for a veterinary syringe filler, what information each one must confirm and what consequence a deficiency has.It does not offer consumption values: these depend on the configuration and must be requested in writing from the manufacturer for each project.

*Electricity, compressed air and drainage connections to the filling line.*
Why the services are defined before themachine
The design of the installation and that of the machine advance in parallel.If the plant defines the electrical connection before knowing the installed power, it may fall short;If the manufacturer defines the consumption without knowing the network, it may propose an incompatible configuration.
The cost of correcting a service after installation is high: civil works, panels, pipes and stops.The cost of defining it beforehand is a meeting and a list of data.
That is why the RFQ must include an auxiliary services section with plant data and questions to the manufacturer.Without this section, the project advances with assumptions made by both parties.
Electricity
Power and voltage
The installation needs to know the installed power, voltage, frequency and number of phases.These data are provided by the manufacturer based on the motors, resistors and controls of the machine.
The installed power is not the average operating power.To size the panel and the protection, the installed power is used;To estimate consumption, the average is used.Confusing them leads to under-protection or over-sizing.
Network protection and quality
The machine must be protected with adequate differential and circuit breaker, and with grounding.It is also advisable to know the quality of the network: voltage drops, harmonics and outages.
A brief outage can restart the control and force the line to be purged.If the plant has frequent outages, it is advisable to provide a backup system for control, although not for production.
Wiring and ducting
The wiring route must be defined before installation: trays, channels, wall passages and connection points.Temporary wiring becomes permanent and complicates maintenance.
Compressed air
Compressed air powers actuators, valves and, in some configurations, blowing or cleaning systems.Pressure, flow, quality and connection point must be defined.
The pressure must remain stable.A pressure drop at the time of rapid movement can cause an actuator to fail to reach its position and the machine to stop without a clear error.
Air quality matters when there is contact with the product or the packaging.Moisture, oil and particles can contaminate.It is advisable to define filtration and dew point according to use.
The connection point must be accessible and with its own shut-off valve.If the machine shares the line with other equipment, the pressure may vary when other equipment starts.

*Line electrical panel with identified protections.*
Vacuum and extraction
Some configurations use vacuum to hold components,to evacuate air or to assist filling.The vacuum must be defined with level, flow rate and connection point.
If the vacuum is generated with pneumatic ejectors, it consumes compressed air and must be added to the calculation.If it is generated with a pump, maintenance and noise must be anticipated.
Vapor or dust extraction is another service that is sometimes forgotten.If the product generates vapors, the room requires ventilation and the machine may require local exhaust.
Water, drainage and cleaning
Water is used for cleaning, and in some cases for cooling or for preparing solutions.Quality, pressure, flow and temperature must be defined.
The drainage must have sufficient capacity and adequate slope.Slow drainage turns the cleaning into a puddle and delays the change of product.
If the cleaning is CIP, the circuit, the injection points and the return must be planned.If it is manual, you must provide hoses, nozzles and space for disassembly.
Environment: temperature, humidity and room
The temperature of the room affects the product and the plastic.Humidity affects static and corrosion.The level of cleanliness of the room affects the risk of contamination.
For sensitive products, it is advisable to define a temperature range and a control system.For products that are not, it is enough to know the seasonal range and adjust the parameters.
The room also needs space for the machine, for maintenance and for storage of tools.A layout that does not allow access requires disassembly for cleaning.
Compressed air quality in detail
Air quality is defined with three parameters: humidity, oil and particles.Each one has a different effect on the line.Moisture corrodes components and promotes microbial growth when air comes into contact with the product.The oil contaminates and can degrade the packaging.The particles clog valves and nozzles.
The dew point is the data that describes humidity.It is not enough to say "dry air": you must indicate at what temperature and pressure it was measured.A dryer that works well in summer may not reach the dew point in winter if it is incorrectly sized.
Filtration is defined by micron and by position.A fine filter protects the valve, but adds pressure loss and must be monitored.A thick filter protects less, but does not clog as quickly.
When the air comes into direct contact with the product, the quality must be higher.In these cases, it is advisable to separate the process air circuit from that of the actuators, so as not to carry contamination from the general network.
How the electrical panel is sized
The panel is sized with the installed power, not with the average power.It is also sized with the starting current of the motors, which can be several times the nominal one.A box adjusted to average consumption trips when starting.
Differential protection must choose its sensitivity according to the environment and the type of drives.Drives generate leakage currents that can trigger a differential that is too sensitive.The manufacturer must indicate the recommended type of protection.
The panel also needs space for future expansions.A line that is expanded with an additional station may require more circuits and more space.Leaving a margin of twenty or thirty percent is common practice.
Circuit identification and panel documentation are part of the deliverable.A panel without a diagram forces each cable to be investigated and delays maintenance.
The layout of the installation
The layout must include the machine, maintenance accesses, the component loading area and the product outlet.It must also include the route of the services and the space for the tools.
A common mistake is to design the layout with the machine in the center and the accesses as residual space.When you have to change a nest or clean a hopper, there is not enough space and maintenance is done with forced postures.
The distance between the machine and the wall must allow opening panels and removing parts.The free height must allow components to be lifted if necessary.And the floor must support the weight and allow cleaning.
The layout must also foresee the flow of personnel and materials: where the product enters, where the waste leaves and where the operator circulates.A cross flow increases the risk of contamination.
What happens when a service is missing at start-up
If electricity is missing, the machine does not start.If there is a lack of air, the actuators do not move or do so only halfway.If drainage is missing, cleaning becomes a problem and product change is delayed.If controlled temperature is missing, the dose varies.
At start-up, each absent service becomes a pending task that delays validation.The machine may be correct and the project may not advance.
That is why it is advisable to make a service checklist before the equipment arrives.This list must be signed by the plant, not just the supplier.
Documentation of services that should be required
The manufacturer must deliver the list of requirements with the data that the plant needs: power, voltage, phases, air pressure and flow, vacuum, water, drainage and environmental conditions.It must also deliver the connection diagram and layout.
The plant must deliver its network data: available capacity, quality, connection points and limitations.With both lists you can close the design.
At start-up, it is advisable to record the measured values: voltage, air pressure, temperature and humidity.This record is the baseline for maintenance.
How the civil works and connections are planned
The civil works include benches, floors, drains and installation steps.If the machine is on a bench, anchors and leveling must be provided.If it is on the ground, resistance and finish must be anticipated.
The connections must reach the final position, not a provisional one.Moving a connection after installing the machine involves cutting, repairing and retesting.
Planning should include each union's deadlines and the order of execution.A delay in drainage can block the installation even if the machine is ready.
What plant data does the manufacturer need?
The manufacturer needs to know the available voltage and frequency, frame capacity, air pressure and flow, vacuum existence, water quality and drainage capacity.You also need the room's temperature and humidity range and space limitations.
With this data you can confirm whether the proposed configuration is compatible or requires adaptations.Without them, the proposal is based on assumptions and the installation reveals the differences.
The list must be completed before manufacturing, not before delivery.A change in voltage after manufacturing the panel involves modifying it or adding a transformer.
How the machine is integrated with existing services
Integration is not just connecting: it is verifying that the connection does not affect other equipment.A shared air that drops in pressure when the machine starts affects the neighboring lines.
The electrical integration must respect the selectivity of protections: the machine must not trip the main switch when a component fails.
The drainage integration must prevent reflux and guarantee the slope.A drain shared with other equipment can return water when they all discharge at the same time.
Table of services and data to be confirmed
| Service | Use on the line | Data to be confirmed | Consequence ifmissing |
|---|---|---|---|
| Electricity | Motors, control, resistors | Power, voltage, phases, protection | Stops, trips, electrical risk |
| Aircompressed | Actuators and valves | Pressure, flow, quality, connection point | Incomplete movements, stops |
| Vacuum | Clamping orevacuation | Level, flow, generation | Non-gripping suction cups, trapped air |
| Water | Cleaning or cooling | Quality, pressure,flow | Poor cleaning, waste |
| Drainage | Cleaning evacuation | Capacity and slope | Puddled water, water delaychange |
| Environment | Product and plastic | Temperature, humidity, room class | Variable doses, static,contamination |
| Space | Operation and maintenance | Layout and access | Difficult maintenance, long stops |
How is it verified in theinstallation
The verification begins before the machine: it is verified that each connection exists, that it has the planned capacity and that it is identified.Afterwards, the connection and operation are checked with the machine empty.
The test with the product is the final one.An installation can comply with the nameplate data and fail under load if the air pressure drops or the temperature rises.
It is advisable to record the measured values at start-up.This record serves as a reference to diagnose subsequent problems.
Frequent errors
- Define the connection without the installed power. The table falls short.
- Share compressed air without its own valve. The pressure varies with other equipment.
- Ignore the qualityfrom the air. Oil and humidity contaminate the product.
- Do not provide drainage. Cleaning becomes a daily problem.
- Do not measure the temperature of the room. The dosage varies between seasons.
- Leave the layout for last. Maintenance becomes uncomfortable andslow.
How King Pack supports
King Pack can deliver the list of services required for the proposed configuration, with the data that must be confirmed by the plant and the installation conditions.The scope includes review of the layout, preparation for start-up and verification of services at the facility.Capacities and limits are confirmed in writing for each project.
Frequently asked questions
Who defines the electrical power? The manufacturer, based on the configuration.The plant confirms the availability and quality of the network.
Can compressed air from the general network be used? Yes, if it meets the pressure, flow and quality.It is advisable to have your own shut-off valve and filter.
Does the machine need a vacuum? It depends on the configuration.Some operations use it for restraint or evacuation;others do not need it.
What room temperature is recommended? The one required by the product and packaging.For sensitive products, it is advisable to control it;for the rest, know the seasonal range.
Is drainage essential? If there is cleaning with water, yes.Without drainage, cleaning is done with buckets and the risk of waste increases.
What service documentation is provided? The list of requirements, the connection diagram and the values measured at start-up.
Can the machine be installed before finishing the work? It is possible, but it is advisable to protect it and leave the final services before the test withproduct.
Related technical resources
For further specification, please review prefilled syringe filling and capping series and guide to choosing a syringe filling machineveterinary.These resources help you refine samples, scope, and acceptance criteria before requesting a proposal.

*Compressed air connection point with shut-off valve and filter.*
Conclusion
TheAncillary services determine the start-up as much as the machine.Electricity, air, vacuum, water, drainage and environment must be defined before installation, with data confirmed by both parties and verified at start-up.Doing so turns an installation into a planned project.